Skip navigation links

Debt Outstanding by Project

As of June 30, 2024

Estimates for projects in Series 2024A, which will be finalized only once all proceeds are spent.

Debt Outstanding by Project
PROJECT DEBT
1855 Place 95,775,024
2019C Savings from Refunding 2010C (19,795,000)
Akers Hall Renovation 15,567,795
Anthony Hall - Repair simulated slate roof 85,657
Armstrong & Bryan Hall Renovations 22,078,511
Auditorium - Alterations to Fairchild Theatre 9,820,605
Bailey and Rather Halls Renovation 22,865,032
Bio Engineering Facility 24,699,398
Biochemistry - HVAC Renovation 6,617,165
BIOMEDICAL & PHYSICAL SCI BLDG/CHILLER 2,578,856
Breslin Berkowitz - Facility Upgrades & Hall of History 479,188
Breslin Bleacher Reconfiguration 261,882
Breslin Student Events Center - Facility Upgrades 26,559,536
Broad Business College Complex Pavilion 19,022,941
Brody Hall Renovations 32,668,717
Brody utility infrastructure improvements 800,834
Butterfield Hall Renovation 11,963,534
Campbell Hall Renovation 28,655,315
Campus Fiber Optic System 1,832,835
Campus Steam Distribution System 53,816,381
Cap Interest/Interest Income/Fees/Issuance Costs (285,546)
Case Hall - Elevator replacement 360,854
Case Hall 1st Floor Renovations of Dining Hall 14,044,556
Cashier's Office Renovations 138,035
CEMS Boiler 3 165,353
Chemistry - HVAC Renovation 4,115,314
Chemistry Lab Renovation (5th floor) 79,963
Chemistry Office Addition 541,491
Chemistry Office Addition Renovations 2007 3,159,615
Chillers 2006 1,809,946
Clinical Center C-Wing HVAC 2,560,118
College of Law 3,239,666
COMM ARTS PARKING RAMP 5 5,132,723
Convert Light T12-T8 1,812,680
Cooling Tower 3 & 4 330,424
Crescent Middlevale 1,206,636
Cyclotron Building - Office Addition - Phase III 10,253,360
Cyclotron Building New High Bay Addition 3,027,902
Cyclotron Low Eng Exp Res and Off Additions 12,079,469
Cyclotron Office Addition 12,969,826
Cyclotron-refrig/cryo projects 240,023
DAIRY CATTLE TEACHING & RESEARCH - CONSTRUCT REPLACEMENT COMPLEX 22,500,000
Data Access in Residential Halls 515,297
DETROIT RESEARCH - CONSTRUCT ORIGINAL BUILDING 126,569,216
Difference between bond debt service and project repayment schedules (54,397,559)
Duffy Daugherty Football - Renovate Team Locker Room and Training Room 1,725,546
Duffy Daugherty SAAC - Skandalaris Football Offices and Demmer Hall of History 1,639,319
EBSP (FIS/HRIS System) 1,561,210
Electrical Support for Units 5 & 6 150,842
Emmons Hall Renovations 9,561,594
Farm Lane Bridge Debt 14,665,316
Farm Lane Underpass 11,400,838
Food Science - HVAC Renovation 7,631,856
FOOD SERVICE EQUIPMENT UPDATE 139,687
Food Stores Roof Replacement 139,997
FRIB 25MW Power Supply 26,303,800
FRIB Cryogenic Assembly Bldg 12,857,693
FRIB High Rigidity Spectrometer and Isotope Harvesting Experimental Vault 23,048,234
FRIB Power Plant Connection 5,953,348
FRIB Utility Relocation Phase I 4,825,560
Grand Rapids Property Purchase 8,303,292
Grand Rapids Research Center 16,768,997
Grand River Parking Ramp 9,506,887
Health, Wellness, and Fitness Center 147,296,912
Healthy Campus / Demonstration Hall - Phase 1 - Multi-Use Court Renovations 1,592,713
Healthy Campus / IM East Gym and Track 1,521,079
Healthy Campus / IM West Turf Arena Renovations 2,935,513
HENRY CENTER EXECUTIVE DEVEL. 243,515
Holden Hall Dining Upgrades 587,501
Hubbard Hall Asbestos 113,939
Hubbard Hall Fire Protection 538,326
HUMAN ECOLOGY SPDC RENOVATION 1,549,324
HUMAN ECOLOGY SUITE 2 RENOVATION 261,884
Innovation and Infrastructure Revolving Fund 500,000,000
Interdisciplinary Science and Technology Building - ISTB 88,264,187
Jenison Field House 2,743,003
Kuali Coeus Research Admin 3,066,174
Landon Renovation 14,699,472
Low NOX Burner Boilers 1-2 '01 487,396
Low Nox Monitoring System 348,012
Mary Mayo renovations 7,154,674
McDonel Hall - Electrical Conversion 155,818
McDonel Hall - Elevator replacements 333,695
MSU MUSEUM INFRASTRUCTURE IMPROVEMENTS - ACCREDITATION 7,290,000
MSU Surplus Store and Recycling Center 4,474,353
MSU Union Renovation 503,496
Multicultural Center 35,000,121
Munn Ice Arena Expansion 11,399,272
MUSIC BUILDING - ADDITION NO. 3 27,303,810
Natural Science Bldg-Window Replc 1,382,323
Natural Science- New Elect Substation 631,427
Old Hort Renovations 413,692
Plant and Environmental Science Construction 29,806,493
Plant Science Expansion 35,576,324
Power & Water -- Major repair & replacement (13 projects) 473,132
Public Art for Debt Funded Projects 110,918
Regional Chill Water Plant Rpl 822,317
Replace Chillers - Hannah Bldg. 484,525
Replace Chillers - Nisbet Bldg. 175,782
Replace Windows- Human Ecology Bldg. 224,863
Road- Wilson & Red Cedar - intersection 1,709,308
Scene Shop Relocation 374,063
Secchia Center 75,551,092
Settlement Debt 359,697,634
Shaw Hall New Dining Center 9,956,540
Shaw Hall Renovation 3,628,353
SHAW LANE PARKING RAMP 1 8,246,841
SHAW/BOGUE INTERSECTION 2000 369,980
SHAW/RED CEDAR INTERSECT 2000 349,800
Snyder/Phillips dorm renovation 19,257,017
South Campus Anaerobic Digester 2,339,100
Spartan Child Dev Ctr 1,225,881
Spartan Stadium - Audio Upgrades 1,312,252
Spartan Stadium - North and East Bowl Restoration 2,454,713
Spartan Stadium North End Zone Addition 1,502,528
Spartan Turf Paved Nursery 284,286
Spartan Village - Re-roof various bldgs 214,782
Spartan Village Electrical 948,140
SRF High Bay Addition Phase I 11,720,536
Stadium Column Repair 2000 873,051
Stadium Column Restoration 303,333
Stadium Expansion 28,057,405
STADIUM NEW TURF 774,266
Stadium North Restoration '02 744,195
Stadium Restoration of East Stands 2000 2,085,094
Stadium South Stands 441,833
Stadium W. Concourse & Columns 489,966
STEM Teaching and Learning Facility 60,867,667
STEM Teaching and Learning Facility - Shaw Lane Power Plant 7,217,196
Stm Dist & Road Rec E/W Circle Drive 6,089,905
Stores Addition 209,317
Student Data Service 509,481
T.B. Simon Power Plant - Modernization - Boilers 16,598,427
T.B. Simon Power Plant - Modernization - Reverse Osmosis 992,083
T.B. Simon Power Plant - Modernization - RICE 44,102,741
T.B. Simon Power Plant - Upgrade Utility Substation 21,256,658
TB Simon Dem Storage Tank #2 222,858
TB Simon Low NOx Burner Installation #3 Boiler 415,659
TB Simon Power Plant - Coal Handling Changes Phase I 14,900,565
TB Simon Power plant addition 18,485,567
TB Simon Power Plant SNCR 1,2,3 1,295,455
Track & Field Turf 1,476,604
Union Mechanical Renovation 566,299
University Village 8,686,688
Utility Distribution -- New elec. sub. sta. for Owen Graduate Center 274,958
Vet. Med. Center - Replace deteriorated roofs 148,773
Veterinary Oncology 142,272
Water Distribution - Campus Water System Improvements 17,282,516
Wells Hall Addition 28,823,090
Wharton Center Expansion 10,662,781
Wilson Hall - Electrical Conversion 185,341
Wilson Hall Alterations (C-102 Auditorium) 132,360
Wilson Rd Phase 2 1,461,019
Wonders Hall - Teaching, Learning, and Student Support Renovation 11,148,163
Grand Total 2,423,740,000